contestada

What is the first phase of the project process?


A. Monitoring


B. Pre-Planning


C. Implementation


D. Planning

Respuesta :

tif21076 tif21076
  • 06-05-2021

Answer:Pre-planning

Explanation:

Answer Link
zlskfrum zlskfrum
  • 06-05-2021

Answer:

Explanation:

Implementation and Monitoring are latter phases of a project.  Pre-planning goes before Planning so the answer is B.

Answer Link

Otras preguntas

On october 1, 2017, miller, inc. made a loan to one of its customers. the customer signed a 6-month note for $100,000 at 13%. how much interest revenue did the
Please help me answer this correctly
The owner of a retail store is tracking his inventory for an annual report. The graph below shows the remaining inventory for a particular item and the number o
Find the area of a rectangle with a diagonal of 20 m and height of 6 m
You did not kill the fish only to keep alive and to sell for food, he thought. you killed him for pride and because you are a fisherman. you loved him when he w
I want an explanation (nothing - something - everything - something)
What feeling would a character most likely experience in this setting
Which organ system works with excretory system to remove carbon dioxide
(These are all different questions) 1. According to the Declaration of Independence, how is the power of government limited or restricted? 2. Which document ha
Suppose that a six-sided die is "loaded" so that any particular even-numbered face is three times as likely to be observed as any particular odd-numbered face.