30 workers can complete a work in 40 days in how many days would 20 men complete the construction​

Respuesta :

s1m1
s1m1 s1m1
  • 25-11-2020

Answer:

27

Step-by-step explanation:

(30 workers/40 days) = (20 workers/x days) cross multiply

30*x=40*20 divide by 30 both sides

x= 800/30

x≈26.67

So they will need 27 days

Answer Link

Otras preguntas

What is the value of the 3 in 34525
1/2h+1/3 (h-6)=5/6h+12 how to solve the problem
list all the basic tenants in Christianity
-5m=4-6m I can't figure out the problem. I need help.
Juanito estimated that 31% of 517 is 204. Is his estimate reasonable? No, because his calculation should be 30% of 520. No, because his calculation should be 40
(Picture) help ASAP need done in less than 15 minutes!!
Who was the commander of the Confederate army? a.)Ulysses S. Grant b.)Stonewall Jackson c.)Robert E. Lee
1.A(n) __ is one in which some or all information is withheld from a subject, the investigator, or both. 2. Conducting an experiment one time is called a(n) __.
Three out of five students said math was their favorite subject. What percentage of students preferred math?
Find the difference between the sum of all 8 positive integral divisors of 66 and the sum of all 8 positive integral divisors of 70.