a field can be cleared by 33 men in 15days. how many more person required if the field has to be cleared 4 days earlier?​

Respuesta :

wsookhuei
wsookhuei wsookhuei
  • 24-10-2020

Answer:

12 men

Step-by-step explanation:

33men x 15 days = the whole project

Let the men that are required be x.

33 x 15 = (15-4)x

495 = 11x

x = 45

Answer Link

Otras preguntas

What kind of molecule is an enzyme? Why are enzymes important in cell?
Draw 2 lines in a triangle. Make 2 triangles and 2 trapezoids.
what is the solution for this inequality -10x <40
Why are the irish famous for drinking?
if 9^x-9^x-1=24, then find the value of (6x)^x
How is 'hearing' a motif in the novel A Separate Peace by John Knowles?
solve using the substitution and elimination method 3a-12b=9 4a-5b=3 can someone please help?
Two of the emission wavelengths in the hydrogen emission spectrum are 410 nm and 434 nm. One of these is due to the n=6 to n=2 transition, and one is due to the
Iliada went to Minewaska state park one day this summer. All of the people at the park were either either hiking or bike riding. There are 178 more hikers than
Two of the emission wavelengths in the hydrogen emission spectrum are 410 nm and 434 nm. One of these is due to the n=6 to n=2 transition, and one is due to the