The critical path of a network is the A. path with the fewest activities. B. path with the most activities. C. shortest time path through the network. D. longest time path through the network.

Respuesta :

uzamamanzoor1271996 uzamamanzoor1271996
  • 24-02-2020

Answer:

D is correct option

Explanation:

D. longest time path through the network.

The sequence of activities within the network with zero total float is called critical path.

Answer Link

Otras preguntas

Oliver is 6 more than twice as old as Sam. If Oliver is 21 how old is Sam? Write an equation to represent the situation.
Can someone please write an equation for me
What is the measurement of this angle?
A committee is formed consisting of one representative from each of the 4 departments (CS-IS-IT-SW) in the computer science college, where the representative fr
Scored 12 out of 39 in the test work out the percentage
A. x=68. y= 75 B. x= 75. v = 68 C. x= 40, y = 68 D. x= 75. y = 70
The length of a rectangular room is 20 times longer than the width . If the perimeter is 588, what are the dimensions of the room
humans tend to obey when asked to do something by an authority figure. which of the following factors makes obedience even more likely?
please help me completing square x^²+2x-24=0​
Write a polynomial function of the least degree that has roots of 3 and (4 + i). Roots: Polynomial Function: