Who is responsible for determining how tasks will be done in a weak matrix project management structure?

Respuesta :

BenitoMarin BenitoMarin
  • 25-01-2020

Answer:

The correct answer is: The functional manager.

Explanation:

A weak matrix project management structure is the type of business organization managed by two executives: the functional manager and the project manager. Both of them work jointly and report to each other accordingly. Out of the two of them, the functional manager is in charge of controlling how work is done within the firm.

Answer Link

Otras preguntas

Help me please (15 points)
A box has a length of 2 yards and a width of 2 yards is a volume is 30 cubic yards what is its height
In "My Father Writes to My Mother," the mother felt when she told her relatives about the postcard from her husband
"paypal is an example of what type of payment system
Who narrates Langston Hughes's short story "Gumption"? A. Oyster, a disgruntled third-person limited narrator describing unjust events B. Hughes himself, a
How can video games facilitate education?
What can I do to lose belly fat? I eat normally, not healthy not unhealthy, exercise everyday and nothing, no change.
Find the total weekly earnings for a waitress with a weekly salary of $275 plus 5% commision on dinners, if the total worth of the dinners she served was $4,000
I need a couple more plz plz plz
Tina wants to save money for school. Tina invests $1,000 in an account that pays an interest rate of 6.75%How many years will it take for the account to reach $