You work as a project coordinator for a design company. on one project, the status report shows that 10 of the work was completed in 90 days. if the work progresses at the same rate, how many days will be required to complete the remainder of the project?
a. 9 days
b. 80 days
c. 100 days
d. 810 days

Respuesta :

Otras preguntas

Why are political parties considered an important part of a democratic political system?
why is geocentric theory is not accurate?
Which letter correctly labels the area claimed by the French as of 1682?
In a democratic government each individual's opinion is of equal importance. a. True b. False
56 less than the quotient of a number and 4 is -52
Decision making is likely to be better informed and more efficient than when it occurs at the local level. a. True b. False
Europe currently enjoys a very high standard of living because?
what is 0.04 as a standard form
With all responsibility for World War I placed on the Germans, they were forced to pay _________, or compensation demanded by the victor from its vanquished foe
What is 19/50 in decimal form