blueflu8713 blueflu8713
  • 25-05-2023
  • Business
contestada

There are four activities on the critical path, and the standard deviations for their durations are 7, 15, 31, and 6 days. The standard deviation of the duration of the critical path is: a. 1271 b. 35.65 c. 59 d. 7.681 e. 14.75

Respuesta :

Otras preguntas

Can someone help me with this page?
why did andrew jackson want the indians to leave their tribes
Assume that Angle A is an acute angle and TAN A = 1.230. the measure of Angle A equals:
Factorise: -1x^2y^2+x^4-2y^4
Mr. Walton ordered 12 pizzas for the art class celebrattion. one fourth of the pizzas had only mushrooms. how many of the pizzas had only mushrroms?
what is the modern names for these countries aegyptus   Britannia  Hispania Sicilia terraconcesis Cyrenaica Italia Belgian
Factorise: -1x^2y^2+x^4-2y^4
What were the lasting legacies of the Crusades?
Chickasaws and cherokees both succeeded in.............
Forty tickets are sold for a raffle with two prizes. You buy two tickets. What is the probability that you will win both prizes?