Complete the following MRP record and provide the planned order releases for Week 3. Lead time is 2 weeks. Safety stock is 4. Use LFL lot sizes. Please show the math in detail.

Part A Week
1 2 3 4 5
Gross Requirements 32 16 34 40 53
Scheduled Receipts 22
Projected On-Hand inventory 56
Planned Order Releases
a. 53
b. 40
c. 0
d. 8

Respuesta :

Otras preguntas

what did Irish and Hungarian nationalists have in common
SAT Question of the Day: The rebel group has long enjoyed total -------: despite having ------- numerous violations, its members have never been punished. (A) a
You buy a game for $40, and the sales tax is $2. What percent of the game price are you paying in sales tax? 4% 5% 8% 20%
how many times greater is one hour than one minute
I'm stuck on number 4... help please?
If a pizza delivery order was placed at 7:15pm with an estimated delivery time frame of 75 minutes. What is the estimated time for the delivery?
What is the noble gas configuration for oxygen?
What is the noble gas configuration for oxygen?
How can I write the formula for strontium fluoride?
What was the religion on the French and Spanish islands? Catholic Protestant Baptist Jewish